Assignment

  • État: Pending
  • Prix: $100
  • Propositions reçues: 3
  • Gagnant: engselgendy

Résumé du concours

Assignment please See the attached file
Consider a project that consists of activities named A, B, ..., M. The following table gives the
predecessors and the duration in days of each of these activities.
Activity Predecessors Duration
A 5
B A 2
C B 2
D A 2
E C 10
F D,C 6
G C 13
H F,E,G 15
I A 2
J E 3
K F,E,I 6
L C,D 2
M D,J,I 3
1. Use the CPM method to find the critical path in this project. Show the details of the
calculation using the graphical representation seen during the lectures.
2. For each activity, give the impact on the completion date of the project if this activity
is delayed by 7 days. Justify your answers. Present the results in a table as follows:
Activity Impact, if delayed by 7 days Justification
A
B
C
D
E
F
G
H
I
J
K
L
M
1

Compétences recommandées

Meilleures propositions de ce concours

Afficher plus de propositions

Tableau de clarification publique

  • aabb39187
    Titulaire du concours
    • il y a 1 an

    please share it with me

    • il y a 1 an
  • bsse1009
    bsse1009
    • il y a 1 an

    I have almost finished the project. Bad luck :)

    • il y a 1 an
    1. aabb39187
      Titulaire du concours
      • il y a 1 an

      ok man

      • il y a 1 an

Comment commencez des concours

  • Publiez votre concours

    Publiez votre concours Rapide et facile

  • Obtenez des tonnes de propositions

    Obtenez des tonnes de propositions De partout dans le monde

  • Attribuez la meilleure proposition

    Attribuez la meilleure proposition Télécharger les fichiers - Facile !

Publier un concours maintenant ou rejoignez-nous maintenant !