Hints:
You may like to consider the following:
• Real and quadrature power losses in each item of plant
• Real and reactive power flows
• Operation of the regulating transformer/tap changers
• Plant ratings
• Bus voltages
• Plant outages
• Relative costs
• Suitability of the models used to represent the items of plant in the network
• Other reinforcement strategies or combinations of strategies.
Objective
You are a planning engineer and have a brief to examine the effect of the addition of shunt capacitors and/or a second duplicate transmission line on the operation of a distribution network to allow for possible increase in the distant 33kV load.
At present, if the existing load at the remote 33 kV busbar rises above the design value of 30 MVA, voltage control problems arise at the B4 busbar causing the voltage to fall below the minimum allowable value of 1.0 pu
Hi
I have read your job post and I believe I have what it takes to give you the best output needed in a short time.I have a wide experience in academic writing and I usually work so hard to meet any givem deadline.
I will be more than glad to work for you if given chance.